|









| |
Key Projects
Provided below are some of Spectrum's key project accomplishments.
SUMTER CEMENT COMPANY –
GREENFIELD PORTLAND CEMENT PLANT
|
|
For the Sumter
Cement Company (SCC), Spectrum prepared a Major Source New Source Review
(NSR) Permit Application (Application) for a Greenfield Portland cement
plant proposed to be located in Center Hill, Florida. The preparation
of the permit application was complex since the proposed new plant had
significant emission increases of all regulated NSR pollutants
associated with Portland cement production. Additionally, this permit
involved the assessment of visibility impairment at two Class I areas
and Lead and Mercury impacts at surrounding Florida State Parks.
|
 |
 |
Spectrum began to
prepare the Application in July 2005 and the
Application was submitted to the Florida Department
of Environmental Protection (FDEP) in September 2005. The FDEP, Environmental Protection
Agency (EPA), Federal Land Manager (FLM), and the public had very few
review comments on the Application. As a result, SCC was able to
receive a Final Permit from the FDEP in early February 2006. In all,
the total permitting process was accomplished in only eight months.
Additionally, the project was completed under budget, as well as ahead
of schedule. |
THE SHERWIN-WILLIAMS
COMPANY – BALTIMORE FACILITY
|
|
With a Title V
Operating Permit renewal, plans to install a new Volatile Organic
Chemical (VOC) and organic Hazardous Air Pollutant (HAP) control
equipment ahead of a rapidly approaching MON- MACT implementation date,
Spectrum was able to prepare a major revisions to the Title V Operating
Permit Renewal, assist with the planning and preparation of the
Permit-to-Construct (PTC) for the RTO/FO control equipment, and
negotiate an agreement with Maryland Department of Environment (MDE) on
a submittal and review/approval schedule. This allowed The
Sherwin-Williams Baltimore Facility to demonstrate that it would be
classified by MDE as a synthetic minor source of HAPs and not be subject
to the MON-MACT regulations. |
|
|
ALCOA EASTALCO WORKS PIER |
| Spectrum
developed
one of the first U.S. Coast Guard (USCG) approved Maritime Facility
Security Plans in the United States for the Alcoa Eastalco Pier
facility. In early 2004, the USCG issued preliminary guidance regarding
the content of the Maritime Facility Security Plans, however due to the
Department of Homeland Security (DHS) mandates, the guidance was
lacking. |
 |
 |
Using a common sense approach, Spectrum
developed a Hazard Analysis, a Maritime
Security Checklist, and a Maritime
Facility Security Plan, as well as
provided the required training to Pier
employees. Alcoa’s Plan was reviewed by
the USCG with minimal comments
and was approved shortly thereafter. The Alcoa Eastalco Works Pier has
since been audited by the USCG and has received very positive feedback
on their implementation. Spectrum
played an integral part in the
implementation and the ongoing support
of maritime security. |
|
Spectrum developed a
Release Prevention, Control and Countermeasures Plan (RPCC) and
emergency response training for Alcoa Eastalco Works and Pier
facilities. The training was then provided to over 500 Eastalco Works’
employees. Spectrum worked with Eastalco to develop a schedule that
would minimize the amount of time that would be taken from production
crews. This involved conducting training during normal working hours,
as well as during swing shift hours (midnight shifts). The training was
educational and provided positive motivation in such as way that
employees felt inclined to make suggestions concerning pollution
prevention and implementation of new procedures to reduce the impacts on
the surrounding environment. |
|
|
Copyright © 2006
Spectrum Environmental Sciences, Inc. |
|
|